Friday, July 4, 2014

Last Week 6/30/14 through 7/4/14

  • The Irwin front greens were mowed several times at a height lower than the previous week. We will continue to lower the mowers as we go forward.
  • We experimented by aerifying one of the greens. Sometimes it is hard to predict how the new sprigs will react. Fortunately, the experiment went very well. We may aerify the rest of the greens on the front next week.
  • After mowing, we topdressed all the greens with a light layer of sand and then fertilized them with 21-0-0 (Ammonium Sulfate)
  • Edged cart paths on the Irwin front
Next Week

  • Continue to lower the height on the new greens.
  • Reposition and/or install several heads in select areas around the Irwin front greens for better irrigation coverage.
  • Fertilize weak areas of turf on the Cate and Back.
Antonio mowing Irwin #6 Green
Day 28


Closeup of Sprigs
Day 28


Hurricane Authur gave us her best shot! We're still standing ... with the exception of a few trees!
Tree down from Hurricane Authur
7.3.14


Is there a cart path under there?
Aftermath from Hurricane Authur


Friday, June 27, 2014





6/27/14



It's easy to see how much they've grown in three weeks!

Day 21
Irwin #6 Green



Day 17
Irwin #6 Green

Day 1
Irwin #6 Green



Day 21
Sprig Closeup



Day 17
Sprig Closeup

Last Week 6/23/14-6/28/16
  • We mowed the new greens two times this week. Once on Monday and again on Thursday. The first two cuts were at (.200"). Our plans are to incrementally lower the mowers until we reach our desired mowing heigth. With the growth we are getting, we'll be mowing everyday in no time!
  • To continue growth and lateral coverage, the greens were fertilized twice and watered throughout the day.
  • After our Monday mowing, we topdressed the greens with a sand/peat blend. Then dragged in the mix with a brush. The topdressing will help fill the voids and smooth the surface.

Next Week 6/30/14-7/4/14
  • Continue to mow, fertilize and topdress the greens.
  • Re-level and sod forward tee on Irwin #5 and middle tee on Irwin #8 (Photos next week)
  • Slice and spike thin area in the fairways and tees. Also hit with fertilizer for quick coverage.







Friday, June 13, 2014

 


Members Club Conversion Update

6/13/14

This week 6/9/14 - 6/15/14

  • We fertilized the sprigs with several different products this week -- 21-0-21, 5-4-5, 0-0-5 and gypsum. This is a great combination of slow and quick release fertilizers, providing a wide range of nutrients essential for growth.
  • Fairways were sprayed with a chemical to remove the remaining ryegrass, allowing our bermudagrass base to flourish and prosper unencumbered.
  • The bridge on Irwin #5 was renovated. The original deck was completely stripped. The old planks were hauled off and disposed of. A new deck was installed and is ready to go.
Just sprigged


One week after sprigging--As you can see, the sprigs have really started to green up

Old Bridge

New Bridge

 Next week 6/16/14 – 6/22/14
·         We will continue to push the sprigs with fertilizer
·         Strip the sod from several tees that are in need of re-leveling
·         Slice and fertilize thin areas in rough
 

Monday, June 9, 2014


Members Club Conversion Update

6/9/14

All the front nine greens are sprigged!!!

     The process went very well. Again, Mother Nature lent a helping hand. About the time the last sprig hit the ground, the sky opened up, drenching us with 1/4" of rain.
     Below are a few photos of the tasks performed during the week.



Spreading soil admendments
Hand-shaking sprigs



Laying sprigs on the practice green
Topdressing the sprigs with a sand and peat mix

Cutting-in the sprigs
 


Water! Water! Water!



Saturday, May 31, 2014

Members Club Conversion Update - 5/30

 Again, the weather cooperated. Thunderstorms loomed in the distance. Fortunately no rain came until the end of the day just after we finished tarping the greens.


Tylor and Alfredo trenching the perimeter


 



Tarping the green with plastic




Plastic drip lines for the fumigant
Burying the tarp in the trench
Completely tarped with square footage of green painted on the turf.




Wednesday, May 28, 2014

MC Conversion Update - 5/28/14


     The conversion from Tifdwarf to MiniVerde has officially started. We are thrilled to have Day One in the books. Mother Nature blessed us with perfect weather. Mid 80s. Sunny. Breezy. Cleanup after verticutting and aerifying went very well.
     We plan to keep the updates coming along with a recap of we've accomplished. Stay tuned!

     Below are a few photos from yesterday's action. Our goal was to remove as much of the old vegetation as possible.

Adam - verticutting the greens - five different directions!




 

Ed and (Drew in the background) blowing off debris after verticutting





Pushing off plugs after aerifying--two directions.

Tuesday, April 15, 2014

Troon site visit

      One of our bi-annual site visits from Troon's senior agronomist was held last week. He toured all four courses and offered recommendations for improvements plantation wide. One of the areas of concern to many are the Mini Verde greens at the Players Club. He assessed our unique circumstances and offered the following as a plan of action.
       Our first and most immediate change will be to raise our mowing heights. We will be raising our height of cut by one hundredth of an inch. This will reduce stress to the plant, ultimately aiding in the recovery phase. We will also be reducing our rolling frequency. This will lessen the burden to the plant and allow it to recuperate faster. These factors will affect the golfer the most. Our green speeds will be moderate for the time being until we show improvement.
        Another area of concern was our nematode counts. We sent samples to the NCDA and our results indicated that our hazard indexes are high. We have since secured a contractor to apply nematicide to our greens. The product is applied directly into the soil and requires 24 hours before re-entry. This will force us to close for an additional day in May. We have scheduled this application for May 13th and will require the course to be closed on May 14th. We apologize for any inconvenience and appreciate your patience.
      Our long term plans on managing the greens will have more of an indirect impact on current conditions. We will continue to assess our managements methods in regards to preparations for winter. We plan to adjust our practices to enter winter healthier than last season. We will also anticipate a long and cold winter versus the traditional mild, temperate season. The core areas of focus will be fertilization, site conditions, irrigation and pesticide use. Again, we appreciate your patience and encourage you to keep following the blog for updates from the agronomy team at St. James.

Tuesday, October 2, 2012

Players Club - Overseed Week

      The Players Club was closed the week of September 25th primarily for overseeding. Although overseeding was our main goal we were also able to complete some other tasks. Here is a recap of last week's projects.

Monday
      While we weren't closed, we were able to begin the overseeding process on Monday afternoon. We applied a wetting agent to the tee tops and green surround. This particular product will aid in water retention at the surface. This will keep the moisture near the surface and readily available for the seed.

Tuesday
      Today was our busiest day of the overseed week. We began the day by topdressing the greens with a medium to heavy layer of straight sand. The heavy application rate was designed to help smooth the greens.
      In the mid morning we started overseeding fairways. This process takes approximately six hours to complete and used 17,500 pounds of ryegrass seed.
      The tees were seeded as well on Tuesday. This was started in the afternoon and generally takes between three and four hours and used 2,000 pounds of ryegrass seed.

Wednesday
      Today we were able to finally correct our turf issues on some of the greens on the back nine. Modern Turf (supplier of our sprigs) agreed to compensate us with 2100 sq ft of MiniVerde sod to replace our weak areas on 12 and 13. Below is a illustrated rundown of the process of resodding of these areas.

Removal of existing weak turf.


Light tilling of soil.


Addition of new soil. A 87/13 sand peat mix.


Using a vibrating tamp to smooth the surface.


Finished sub grade.


Aligning the new sod.

Unrolling the sod

Tucking the seams.
Finished surface.
      Sodding these areas on 12 and 13 took almost twelve hours total. We finished up on number 13 on Thursday at 11 A.M.. As of posting, these areas will be played as a free drop. Should your ball lie on these areas of the green you may place the ball at some point on the green no nearer to the hole.

Thursday
      We wrapped up our sod project in the morning and refocused our attention to overseeding. We overseeded green surrounds in the afternoon on Thursday. This task takes roughly six hours and used 4,000 pounds of ryegrass seed.

Friday
      Today we applied our preemergent herbicide to the perimeters of all of the overseeded turf. This product will prevent any wayward ryegrass seed from germinating outside of the target overseed areas. The application of this product is done with a walk behind sprayer and typically takes about three to four hours.

      Overall we had an excellent closed week for overseeding. Mother Nature cooperated enough to allow us the time to complete all of our goals. Our focus can now shift to preparation for the Member-Guest tournament in late October. Keep following the blog for more updates from the St. James agronomy team.

Saturday, June 30, 2012

PC Conversion Update - 6/30/12

      Water, water, and water some more. That has been the theme at the Players Club over the latter part of the week. We will continue the frequent watering through next week. As the greens become more established, the frequency of watering will decrease and the amounts will increase.
      Along with nursing the greens we were able to accomplish some other goals around the course. Here is a rundown of last week and a look ahead to next.

Last Week 6/24-6/30
  • Planted the MiniVerde sprigs. In case you missed it, here is an overview of the process.
  • Repaired multiple minor irrigation issues around the course. This is a never ending task with 900+ sprinkler heads.
  • Landscaped and sodded the surround of our nursery green. The nursery green is located near our maintenance facility. Here is a picture of that complex.  


  • Cut back some overgrown areas around tees and greens.
  • Applied fertilizer and wetting agent to the bunker faces.
      
Next Week 7/1-7/7
  • Apply fertilizer to the greens. The timing will be based upon their condition. The amount of green tissue at the surface will determine the proper day for fertilization.
  • Roll the greens.*
  • Lightly verticut the greens.*
  • Apply a light topdressing to the greens.*
  • Spray growth regulator on the fairways, tees and rough. This will limit the amount of topgrowth, which in turn reduces scalping and improves overall appearance.
* Tentative based on condition of the greens.

      The greens are currently in a day to day stage. As stated, we are watering frequently and constantly observing their progress. Here are a couple photos of the surfaces Friday.


Above is a photo from eye level. Here you can not see much difference from Tuesday. One change is the the topdressing has settled. This settling has exposed more sprigs to the surface. Although subtle while standing, there are many changes happening at ground level.



Here is a picture from the surface. There is a huge difference when you view the green from this level. You can see the new growth emerging from the sprigs. This was very encouraging to us on Friday. Modern Turf (sprig supplier) told us not to expect any green-up for one week.

      The encouraging green-up ensures us that the conversion is right on schedule. With six weeks until opening, we are confident that the greens will be in excellent condition on August 13th. If you haven't already, come out and see the greens next week. And as always, follow the blog for updates on the conversion and other maintenance projects at St. James.

      One more note with concerns to observing the greens. We run our green's irrigation manually everyday from 6:00-10:30 A.M. and 12:30-4:00 P.M. Our computer system runs the irrigation from 10:30 A.M. until 12:30 P.M. and from 4:00 P.M. until dusk. We are not in control of the cycles during these times. We do not recommend checking on the greens at the times in bold. The best times to stop by and see the greens is from 8:00-10:00 A.M. and 1:00-3:00 P.M.



     

Wednesday, June 27, 2012

PC Conversion Update - 6/27

      The day has finally come and gone. The sprigs arrived around 12:00 on Monday. They came in a refrigerated tractor-trailer. After a short training session, we began planting around 1:00. We were able to complete the back nine (w/pg) around 6:30 Monday evening. We started the front nine at 7:00 Tuesday and finished up on the nursery green at 2:00. Here are some pictures and descriptions of exactly what transpired over the last two days.

      Prior to planting we applied two fertilizers and a pre-emergent herbicide to the greens. The fertilizers were applied to be readily available for the sprigs upon planting. We used a (46-0-0) and  (7-23-19) fertilizer for this application. These fertilizers were selected based on a variety of factors associated with our specific site. The pre-m herbicide was for control of crabgrass and goosegrass. Oxidiazon is the common name of the product we used. This product is the only pre-m that will not interfere with the establishment of new turf.

      Below are pictures describing the various stages of the sprig planting process. The first picture shows a full bag of sprigs as they arrived. These bags are placed all over the surface of the green. We used 15-20 bags per green.




     The bags were then placed onto tarps for opening. The tarp prevented foot and hand marks in the surface from grabbing the sprigs. 




 
 Here is an opened bag dumped atop the tarp. The sprigs were compacted tightly in the burlap sacks, therefore we had to spread the bag over the tarp in order to seperate the sprigs.



 

  This photo shows the laying of the sprigs. It is just as it sounds. We would grab handfuls of sprigs a shake them out all over the surface. This process was similar to spreading bales of straw. 





Below you can see the green take shape. We had roughly 10-15 people per green spreading the sprigs. Each green took approximately 30-40 minutes to spread.







Near completion we began to apply water to the sprigs. This helped to keep the sprigs in place until we could apply water with the overhead irrigation. Below you can see a green in the final stage of sprig laying.





The next step was to slice the sprigs into the surface. We sliced the sprigs in two directions. This process helps to promote good soil to sprig contact. The slicing also helps to keep the sprigs intact on the surface. This theory was tested and proven Monday night. We received two inches of rain and had zero displacement of sprigs.






After slicing, we topdressed the greens. We applied a heavy layer of sand & peat on top of the sprigs. The topdressing provided the sprigs with the proper soil medium to encourage growth. Below you can see a photo of the green being topdressed.




Below is a photo of the topdressed surface. You can see how the sprigs and sand/peat mixture have become incorporated onto the soil surface. 


The final stage in the sprig planting was to roll. The rolling helps in smoothing the surface and promoting soil to sprig contact. Below is a picture of our roller in action.




And then finally, water. Watering, rolling and fertilizer will be our primary focus over the coming weeks. At this point the sprigs need to be treated like seeds. We will apply light amounts of water at frequent intervals to establish the sprigs. At that point we will begin to reduce the frequency of water application.



      After months of preparation and planning, the sprigs have finally been laid. Our focus now shifts to establishment and maintenance of the green surfaces. I encourage all to stop by and check on the new greens. And always, continue to follow the blog for updates on their progress. Also, follow along on Twitter @stjamesturf.